|
City
Manager's Column: A More Modest Street Program Proposal.
2/10/03
Some of you may have noticed the January 2003 web
site column that I wrote. It
talked about a large scale street program that involved bonding and
the use of assessments as a means for financing such projects.
This column offers a more modest
approach that attempts to provide a program that does not use
bonding or assessments, but, instead, tries to live within what we
expect to receive from our annual allocations of federal highway
funds and Road Use Tax.
The basic components of a more
modest strategy might include:
1.)
Use Our Federal Highway Funds In Coordination With Local
Funds. In
previous years, the City only received a small annual
"sub-allocation" of federal highway funds.
This amounted to about $19,000 per year.
The bulk of all other federal highway funds was awarded
competitively throughout our multi-county region.
Since Maquoketa's projects didn't score well in this
competition, few projects were done here.
A few years ago, the members of our region voted to allocate federal
money according to population. This
was better for Maquoketa than the previous competitive process
because it assures us an annual allocation of about $80,000-$100,000
per year in federal highway funds.
For every dollar spent on a
project that uses federal funds, $.80 in federal money has to be
matched by $.20 in local money.
The local match can come from bonding, assessments, general
fund tax revenue, or Road Use Tax (RUT.)
When possible, the use of RUT is preferable because it
doesn't impact property taxes--it comes from the State of Iowa.
When the change from a competitive system to a population system was
made, the City started banking its funds for a project to
reconstruct
the southern half of Western Avenue
. This project was
estimated to cost, not counting $91,250 for new water main, about
$505,000. Of this,
$404,000 will be federal and about $101,000 will be local.
It took us about 4 years to "bank" both our federal
money and matching local money, in this case, RUT.
The project on Western will have enough funding to proceed in
FY 03-04.
The following streets are
qualified to use federal highway funds for projects:
Western
Ave
E
Summit/W Summit
Jacobsen
Drive
N
Main/S Main
E
Maple
S
Matteson Ave from E Summit to E Maple
S
Vermont/N Vermont
W
Quarry/E Quarry from N Vermont to Anderson
Anderson
Pershing
Road
N
2nd Street from W Platt to W Quarry
As long as projects in our
region receive federal highway funds on a population basis, we
should try to match projects on these streets as such funding
becomes available. We
should be prepared to "bank" RUT that we receive annually
to serve as our match.
2.)
Projects on
North Street, N
Olive, and N Otto.
For the past few years, we've also been saving portions of
our annual allocations of RUT to do projects on these streets.
To some degree, each street also needs either water main or
sanitary sewer work, so we have also been setting aside money in our
water and wastewater capital improvement plans or CIPs for these
purposes.
According to our timetable, we'd
have enough money saved to do a project on N Otto in FY 04-05 and
North Street
and N Olive in FY 05-06.
The advantage of using this
timetable is that streets are done as soon as we can pay for them.
But, the disadvantage in this particular case might be the
close proximity of the streets that are involved.
For example, it might be a better use of funds and the
bidding process to have all of these projects bid for completion as
one project rather than two.
3.)
Alternatives to Seal Coating.
Our current RUT budget for FY 03-04 has about $97,000
available for projects such as road maintenance.
Recently, the Public Works Dept
took measurements of several streets that they have viewed with an
area paving company. The paving
company then provided us with cost estimates for the milling
off of old asphalt, transporting it to a new location for a new use,
and replacing it with an asphalt overlay of 2.25 inches.
I should emphasize that the
figures we were given were budgetary estimates--actually bidding
would have to take place later.
The estimates also don't include the cost of patching and the
relocation/lowering of fixtures, manholes, and water values.
These are the estimates that we
received:
a.)
Complete milling of
Kathey Drive
,
Susan Drive
, and the intersection of E Grove, Kathey Drive, and Butternut
Approx 5075 SY
Milling 5075 SY
$ 6,343.75
Hot Mix Asphalt, 656 tons
$33,520.00
Mobilization/Traffic
$ 2,500.00
TOTAL
$42,363.75
b.)
Overlay of
E Summit
from
Matteson Ave
to
Birch Drive
Approx 7679 SY
Milling Butt Joints
$ 1,200.00
Hot Mix Asphalt, 993 tons
$44,873.00
Mobilization/Traffic
$ 2,500.00
TOTAL
$48,873.00
c.) Curb Reveal and
Overlay
E Summit
from
Matteson Ave
to
S Main
Approx 4698 SY
Milling 3240 SY
$ 6,107.40
Hot Mix Asphalt, 607 tons
$28,395.00
Mobilization/Traffic
$ 2,500.00
TOTAL
$37,022.40
d.)
Curb Reveal and Overlay of
W Summit
from
S Main
to
Western Ave
Approx 11,986 SY
Milling 7992 SY
$10,390.00
Hot Mix Asphalt, 1550 tons
$71,933.00
Mobilization/Traffic
$ 3,500.00
TOTAL
$85,823.00
e.)
S Jones from Platt to
Summit
: Milling to a depth of
4" across entire cross section and paving with 2.25" of Hot
Mix Asphalt
Approx 8532 SY
Milling 8532 SY
$12,800.00
Hot Mix Asphalt, 1105 tons
$55,355.00
Mobilization/Traffic
$ 3,500.00
TOTAL
$71,655.00
f.)
N 2nd Street
from
James Street
to Platt: Diamond
grinding of existing concrete until smoothed then concrete overlay
Lump sum
$13,136.00
g.)
S 2nd Street
from Platt to
Pleasant Street
: Diamond grinding of
existing concrete until smoothed then concrete overlay
Lump sum
$16,708.00
4.)
Putting a Program Together.
There might be other streets that the Council will want to
look at, but this is one possible program that we might try with the
streets listed above. Remember,
this table is based on timing projects as RUT and federal money
comes in and is available. By
doing this, we can avoid bonding and assessments.
|
PROJECT |
TOTAL |
FEDERAL |
LOCAL/RUT |
| FY
03-04 |
|
|
|
|
| Western
Ave |
Reconstruct |
$505,000 |
$404,000 |
$101,000 |
| Kathey/Susan |
Mill/Overlay |
$42,363 |
$0
|
$42,363 |
|
|
|
|
|
| FY
04-05 |
|
|
|
|
| E
Summit: Birch-Main |
Mill/Overlay |
$85,895 |
$68,716 |
$17,179 |
| S
Jones |
Mill/Overlay |
$71,655 |
$0 |
$71,655 |
| S
2nd |
Grind/Overlay |
$16,708 |
$0 |
$16,708 |
| N
2nd |
Grind/Overlay |
$13,136 |
$10,509 |
$2,627 |
|
|
|
|
|
| FY
05-06 |
|
|
|
|
| North/N
Otto/N Olive |
Reconstruct |
$672,860 |
$0 |
$672,860 |
| W
Summit |
Mill/Overlay |
$85,823 |
$68,658 |
$17,165 |
|
|
|
|
|
| TOTALS |
|
$1,493,440 |
$551,883 |
$941,557 |
|
|
|
|
|
| %
of Totals |
|
100% |
37% |
63% |
Footnotes:
--This table assumes that about
$100,000 in RUT is available each year to cash-flow these projects.
If this happens, at the end of FY 05-06, about $132,303
should still be available for projects that could still be
identified for that year.
--The balance for federal money
at the end of FY 05-06 is projected at approximately $33,480.
--Some of our available RUT
could be used for seal coating if the goal is to extend the life of
a street in order to buy it time until it can be milled and
overlayed.
--Millings of old asphalt can be
used on parking lots and alleys.
The Public Works Dept can apply them.
--The milling and overlay
projects do not assume cost estimates for added work such as placing
thicker asphalt in some areas or needing to "core out" and
replace damaged base stone.
--Milling and overlaying
projects, like the ones proposed, do not require the services of an
engineer.
--This plan doesn't make any
assumptions about the condition of underground utilities.
However, it should be our practice to televise, or check with
a camera, underground utilities before projects are pursued.
--Finally, this plan suggests
doing the projects North St/N Otto/N Olive all in the same year, or
FY 05-06. The cost
listed for this overall project reflects the costs of the streets,
storm main, miscellaneous, and engineering.
This cost doesn't include the water or sewer main.
However, all such costs are already in our water and
wastewater CIPs and funding will be in place when it is needed.
|