|
City Manager's Column: Creating a
Street Replacement Program and a Way to Pay for It--One Possible
Scenario.
1/9/03
In a separate article in this month's edition of
our web site, we presented a run-down of our Mayor and City
Council's top goals for the coming year. I would like to say a few
things about the goal that came in second place.
In that goal, the Council identified the need to
create a street replacement program, including a way to finance
it.
That's a tough goal.
For some years, the Council has been looking for
an alternative to our current practice of maintaining streets
through the use of seal coating. As many of you know, seal coating
is the process of taking an asphalt or a previously seal coated
street and applying a thin layer of tar to it with rock chips. The
chips are pressed into the tar.
The process helps to seal cracks that may have
formed in previous years, and, hopefully, extends the life of the
street before major reconstruction has to be done.
Probably the best example that I have heard as to
why towns use seal coat was offered by Neil Morehead a few years ago
when he was on the Council. He likened it to when people paint the
exteriors of their homes when the previous paint wears off. As Neil
observed, the paint isn't a substitute for a home's wood siding, but
it protects it and extends its life.
Depending on the traffic on a given street and the
street's previous condition, a layer of seal coat might last about 4
to 8 years before being redone.
But, there are problems to seal coating. While it
might buy time for a street, it doesn't fix fundamental flaws that
may have developed in the street. Also, as we've seen on streets
like S Jones, layer after layer of seal coating can fill the street
to the point that the curb is essentially gone.
And, as I mentioned above, while seal coating buys
time for street, it is not an alternative to eventual street
reconstruction.
In our current fiscal year, we are expected to
receive $469,356 in Road Use Tax. That is a lot of money, but after
we take from that funding that is also used to pay for public works
personnel and departmental operating expenses ($127,000;) annual
debt ($32,195) on the N Main Street storm sewer project of 1999; the
capital improvement plan to replace equipment and provide partial
funding of future projects on Western Ave, North Street, N Otto, and
N Olive ($234,690;) and miscellaneous projects ($35,500;) that
leaves only about $40,000 for other types of annual street
maintenance work.
The $127,000 that is listed above is basically our
use of Road Use Tax or RUT to balance our general fund's operating
budget. We use this money as an alternative to raising property
taxes for an equal amount. In previous years, we have used as much
as $170,000 from RUT to balance our general fund budget.
Therefore, our use of RUT helps to keep our tax
rate lower, but has the trade off of giving us that much less to use
on our streets.
So, with only about $40,000 to use for street
maintenance each year, all we can really afford to do is seal coat
until we save up enough other RUT funds to do something more
permanent. The problem is that we are not saving enough of our Road
Use Tax funds at a fast pace to do anything on a wide enough scale
before seal coating is no longer the answer on some streets.
Currently, we do not use special assessments for
street projects. In the City Council minutes from the 1960's, there
are numerous references to the use of special assessments for street
projects. Personally, I'm not a big fan of assessments because, if
they are seen as being too high on the abutting properties, people
will fight having street projects done until their streets are in
absolute tatters.
We also don't use property taxes for street
projects.
For the last several years, we have used cash on
hand, RUT, and tax-increment financing (or TIF) to finance street
projects. Each has problems: Cash on hand eventually runs out and
has to be replaced. Our RUT is stretched too thin. And, TIF only
works on newer developments where there are new taxes to capture.
So, what could we do? Here's an example, but
please remember: The ideas expressed below have not been presented
to or approved by the City Council. Also, interest rates and the way
that debt is amortized are variable. Also, the actual costs for
projects may come in differently from the estimates that I'm about
to use.
A few years ago, I asked IIW Engineering for some
generalized figures about what it costs to reconstruct a street. I
was told that, on the average, it cost $228.33 per lineal foot to
reconstruct a 31' wide street with 6 inches of concrete on a 6-inch
crushed stone base. The figure of $228.33 per foot includes the cost
of engineering, but does not include the replacement cost of any
underground utilities. (If street, water main, and sewer main
replacements are needed the cost jumps to $341.00 per lineal foot.)
If we looked at projects in the form of 6-year
timeframes of $1,000,000 apiece, we could reconstruct about 4380
feet of street every 6 years. At 4.5% interest, annual debt payments
would average $202,000 per year. Within this, there would be
principal payments that would average about $167,000 per year and
interest payments that would average about $35,000 per year.
We could feasibly pay for each year's principal
payment from RUT and have some money left over for seal coat or
slurry to use on streets that are waiting for their turns for
reconstruction.
We could then do one of the following with the
interest costs:
a.) Assuming that a street project benefits that
whole town and not just the abutting property, the cost of each
year's interest payment could be paid for out of the general fund
budget. In this scenario, annual interest costs average about
$35,000 per year. If we used property taxes to pay for this, it
would add about 31 cents per thousand dollars of assessed value to
everyone's taxes.
b.) We could assess one-half and tax for one-half
the cost of the interest. In other words, in this scenario, the
total interest we'd owe would be about $213,827. If the project
really involved about 4380 lineal feet, there'd be double that or
about 8760 "running" feet because each street runs past
property on both sides of it. $213,827 divided by 8760 equals about
$24.41 per running foot. One half of that would be $12.20 per
running foot. So, generally speaking, an 80-foot wide lot would be
assessed $976.
The City's fiscal year of 2003-2004 could be
significant for the City. During this time, we have about $470,000
in federal highway funds that are coming due for our use. The
Council has already designated a project for these funds on Western
Ave. A portion of these funds could also be used to fund repairs to
E Summit Street on both sides of the bridge.
Federal money plus city funds could make for some
significant improvements.
*
* *
Around mid-December, I had a meeting scheduled
with Pat Callahan, a former Maquoketa city manager who has since
ascended to the higher heaven of professional municipal consulting.
Pat was dropping by to discuss the Mayor and City
Council's annual goal-setting session that he would be facilitating
later that night.
Our new receptionist, Sue, came to my office door.
"Brian, Dr. Bybee is here for your 11 o'clock
appointment."
"What?" I asked.
"Dr. Bybee is here for your 11 o'clock
appointment," she repeated.
"I don't have an appointment with him. But,
Pat Callahan is suppose to be stopping by."
"Is that who that is? I think he looks like
Dr. Bybee."
When Pat and I finished our meeting, we arranged a
little scene. I followed Pat out of my office. We stopped by Sue's
desk. Pat then turned to me and said:
"Now, remember to take those ear drops twice
a day, then call me in a week."
We then looked and saw that Sue was watching and
listening to us. She then caught on to what we were doing and said:
"Is this what you do all day…figure up ways
to give the 'little people' a hard time?"
Actually, it isn't. It's only a side benefit.
|